MBCP REQUEST FOR PROPOSAL

Front of the Meter Battery Energy Storage System Capacity and Energy Delivery

Monterey Bay Community Power (MBCP) is seeking to acquire up to 100 MWs of Capacity, Energy, and any associated Ancillary Products from battery storage projects in the state of California, or at the first point of interconnection, with deliveries beginning as early as January 1st, 2021, but no later than December 31st, 2022.
points_divider
Supporting Documents:
points_divider

Content:

Monterey Bay Community Power (MBCP) hereby issues this Request for Offers for the sale and purchase of Front of the Meter (FTM) Battery Energy Storage System (BESS) capacity and energy delivery consistent with the terms and provisions in this Request for Offers (RFO). MBCP is seeking to acquire up to 100 MWs of Capacity, Energy, and any associated Ancillary Products from battery storage projects in the state of California, or at the first point of interconnection, with deliveries beginning as early as January 1st, 2021, but no later than December 31st, 2022, on the terms set forth herein, to help MBCP meet its long-term portfolio objectives.

Activity Scheduled Date
Issuance of RFO September 13, 2019
Seller Webinar
Seller Webinar Presentation
September 27, 2019 at 1:00 PM PPT
Deadline to submit questions October 2, 2019 at 5:00 PM PPT
Responses to questions provided October 8, 2019
Responses due to MBCP October 11, 2019 at 5:00PM PPT
Notification of final shortlisted Offers (Tentative) October 2019
PPA negotiations October 2019 – February 2020
Execution of PPA February 2020